(→Methods/Results: In Progress: added milestones) |
(→Milestones: changed formatting) |
||
Line 67: | Line 67: | ||
*Review database schema diagram with Coder | *Review database schema diagram with Coder | ||
| Thursday, 12:00am, 12/06/19 | | Thursday, 12:00am, 12/06/19 | ||
− | | ''INCOMPLETE'' | + | | '''INCOMPLETE''' |
|- | |- | ||
| Final Presentation | | Final Presentation |
Revision as of 19:19, 25 November 2019
Contents
Electronic Lab Notebook
Purpose
The purpose of this week's assignment is to discuss the progress that has been done. Roles for each team member would be explained a bit more and the goals of completing certain tasks would be completed for this week. These tasks include finalizing the data analysis portion. As a QA, the major task is making sure the data analysts are doing okay and to help out as much as possible.
Methods/Results: In Progress
November 21, 2019
- For this week, our group decided to complete some of our milestones and deliverables by Thursday's date.
- Reviewed the work that the data analysts did to make sure there weren't any errors that were made.
- Thanks to a great team, data analysts caught some things as well that were wrong.
- Made sure the metadata was up to date and asked to have few things clarified.
- Reminded to write summaries down for group's assignment.
November 26, 2019
- Double checked the work of the data analysts again to see if things look okay.
- Added more things to the template
- Created more links that follow deliverables' requirements
- Copied and pasted questions that will be answered in the future from Dahlquist's weekly assignments
- Checked to see group's page is up to date.
Milestones
Milestones | Due Date | Complete/Incomplete |
---|---|---|
Annotated Bibliography
|
Tuesday, 12:00am, 11/12/19 | COMPLETE |
Journal Club Presentation
|
Thursday, 12:00am, 11/14/19 | COMPLETE |
Working with Data Analysts to Understand Microarray Dataset
|
Tuesday, 12:00am, 11/26/19 | COMPLETE |
Making Sure Expression Data has Both Sytematic Name and Standard Name ID's
|
Tuesday, 12:00am, 11/26/19 | COMPLETE |
Work with Coder/Designers to Design a Database to Store Time-course Microarray Data from Four Sources
|
Tuesday, 12:00am, 12/03/19 | INCOMPLETE |
Validation and Quality Assurance on Database
|
Thursday, 12:00am, 12/06/19 | INCOMPLETE |
Final Documentation
|
Thursday, 12:00am, 12/06/19 | INCOMPLETE |
Final Presentation | Tuesday, 12:00am, 12/10/19 | INCOMPLETE |
Report submitted | Friday, 4:00 pm, 12/13/19 | INCOMPLETE |
Data and Files
Conclusion
Overall, it has been a bit difficult to contribute to the group because there isn't much a QA can do in the first few stages of this project. However, in the background, there have been reviewing and making sure things are being submitted on time. More messages will be sent out to group members to make sure things are being submitted on time so everyone can get the points they deserve. For the next week, the plan is to continue hitting the milestones and completing the checklist for the group's deliverables.